The Projects most significant risks and their mitigation should have upper management approval and be communicated to all stakeholders as early in the design process as possible. Otherwise, late changes to a risk mitigation strategy, such as reverse engineering a vehicle recovery solution after its design has been baselined, may actually increase the Project's overall risk.
https://llis.nasa.gov/lesson/1293